The Carbon County Planning Commission convened on Tuesday, Nov. 10, for the body’s regularly scheduled meeting. The main item on the agenda was a recommendation for a conditional use permit for rPlus Energies Diamond Mountain Energy Center, planned roughly 4 miles south of Wellington. Following a presentation from rPlus and a question-and-answer period with the commissioners, the project’s CUP received a favorable recommendation.
Representing rPlus, Theresa Foxley presented to the commissioners, explaining the scope of the project. Foxley shared that the company was behind the Graphite and RC solar projects and the Green River Energy Center, which was commissioned earlier in 2026. The Diamond Mountain project would be a 450-megawatt solar project with battery storage.
She also explained that the project would be an economic driver, stating that the project would create “a significant amount of new tax revenue for the county and the taxing entities within the county, including the school district.”
She cited the Green River Energy Center as an example, which is a similar size to the planned Diamond Mountain project, stating that over 20 years the project is expected to generate $60 million in local tax revenues.
Foxley also highlighted rPlus’ community involvement, the Local First Scholarship and the Energy First Scholarship at Utah State University Eastern, as well as other community-based events.
Moving to questions from the board, Foxley was asked to explain the difference between Diamond Mountain and the RC and Graphite projects. “So the RC project is smaller than this project, but it’s similar in the respect that it is also a solar plus battery project. And the reason we differentiate RC from Graphite is that the Graphite project was a solar-only project. In the time since that project was developed, the battery technology, or the BESS technology, has really improved such that most of the project developers like us now are proposing and planning to bring that BESS component into it.” She added that the Diamond Mountain project is approximately five times bigger than the RC project.
Foxley also answered a question regarding the company’s business model. “The first project that we developed in Carbon County, the Graphite project, is now under new ownership. However, it was the first project we brought online as rPlus Energies, and so we have a lot of emotional attachment to that project, and you know, sometimes take calls from interested stakeholders in the community about it. Were we ever in the position to buy that project back we would do it in a heartbeat. In the time since we developed the Graphite project, we have transitioned our business model so that now rPlus is the developer, owner, and operator of these projects, and we would intend to own this project.”
Moving to conditions of the project, the CUP application states that the company must maintain road conditions in the area and repair any damage caused by the project, provide an environmental assessment from the Bureau of Land Management, and submit a decommissioning and reclamation plan for the project, among other items.
Ultimately, the body voted unanimously to provide a positive recommendation for the CUP.
Because the Planning Commission serves in an advisory capacity, the application now advances to the Carbon County Commission for final consideration.